How a BESS Addition Can Push Your Non-Registered Generator into Registration Territory
GridSME Reliability & Compliance Team • Jan 04, 2021

GridSME has been talking to a number of existing generator owners who plan on greatly enhancing the flexibility of their PV and Wind generation facilities through the addition of Battery Energy Storage Systems (BESS). There are many generators who are interconnected at >100 kV who do not have nameplates >75 MVA and are, therefore, not required to register with NERC as BES assets.

Generator owners should be aware that the addition of battery storage contributes to the nameplate capacity for consideration for registration. Even if it does not change the deliverability to the BES from an MVA perspective. An opinion from one of the Regional Entities confirmed that all nameplate capacity would be considered towards the >75 MVA threshold.

Example – An existing >100 kV interconnected 50 MVA Solar PV facility is adding 50 MVA of battery storage capability, but is not changing its Generator Interconnection Agreement (GIA) deliverability to the POI of say 45 MW. Per the NERC BES
Definition, this resource now has 100 MVA of nameplate capacity and must register with NERC as a BES asset even though its deliverability to the PO has not changed.

This may be a startling fact to those considering adding flexibility to existing facilities or planning for new construction that previously would have been thought to be under the NERC registration threshold. Please reach out to GridSME for further guidance to generation facilities and discussion about your unique facility characteristics.

NERC BES Definition Inclusion I4 states:
I4 - Dispersed power producing resources that aggregate to a total capacity greater than 75 MVA (gross nameplate     rating), and that are connected through a system designed primarily for delivering such capacity to a common point of       connection at a voltage of 100 kV or above.

Thus, the facilities designated as BES are:

  • The individual resources, and
  • The system designed primarily for delivering capacity from the point where those resources aggregate to greater          than 75 MVA to a common point of connection at a voltage of 100 kV or above.


From the NERC Bulk Electric System Definition Reference Document, August 2018, both BESS and solar PV are applicable under I4.

Dispersed power producing resources are small-scale power generation technologies that use a system designed primarily for aggregating capacity providing an alternative to, or an enhancement of, the traditional electric power system. Examples could include, but are not limited to: solar, geothermal, energy storage, flywheels, wind, microturbines, and fuel cells.

There are solar panels and power lines in the background.
By Torri Pugh 02 May, 2024
Insights from GridSME: California's Renewable Energy Roadmap GridSME's Subject Matter Experts, Gary Brown and Lowell Watros, contributed valuable insights to this article for Reuters. Their expertise helped provide information and analysis on California's latest grid plan, particularly concerning grid improvements, renewable energy projects, and an expected surge in solar and storage projects. With their input, the article offers a comprehensive understanding of the developments in California's energy landscape and the implications for the renewable energy sector. Below are some of the key insights and takeaways from the article.
By Torri Pugh 30 Apr, 2024
🚨 NERC Alert: Assessing 6 GHz Communication Impact on Electric Industry NERC has issued a Level 2 Alert concerning 6 GHz Communication Penetration in the Electric Industry, targeting Distribution Providers (DP), Distribution Provider UFLS-Only (DP-UFLS), Generator Owners (GO), and Transmission Owners (TO). The alert aims to evaluate reliance on 6 GHz technology and potential interference severity. Respondents must address a series of questions by July 8, 2024, to assess the situation comprehensively. Although only registered entities can respond directly, the alert is publicly available. Action items include acknowledging the alert and completing the questionnaire. Recommendations include identifying critical circuits and conducting baseline performance tests. It's crucial to note that these recommendations are distinct from requirements, as clarified by NERC. This alert underscores the necessity of assessing 6 GHz communication's impact on industry reliability and security. Stakeholders should stay informed and promptly address the alert's requirements. For further details, visit NERC's website: Link . See our LinkedIn post about the NERC Alert: here .
Share by: